A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results: Observation 1 2 3 4 5 Time (Seconds) 84 76 80 84 76 What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of job time is used?
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.