Electronics Assembly Inc. is a contract manufacturer that assembles consumer electronics for a number of companies. Currently, the operations manager is assessing the capacity requirements as input into a bid for a job to assemble cell phones for a major global company. The company would assemble three models of cell phones in the same assembly cell. Setup time between the phones is negligible. Electronics Assembly Inc. operates two 8-hour shifts for 275 days per year.

a. Calculate total capacity required by line.

b. Determine the total operating time available

c. Calculate the total number of assembly cells.

+4
Answers (1)
  1. 5 July, 23:00
    0
    a. Capacity required

    1776600 minutes per year

    b. Total operating time available 264000 minutes per year

    c. Assembly cells required 7.00cells

    Explanation:

    A. capacity required = sum of demand + processing time

    B. Number of shifts x hours of shifts x days if shift.

    C. Assembly cells = total time required / total time available in a year
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Electronics Assembly Inc. is a contract manufacturer that assembles consumer electronics for a number of companies. Currently, the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.