A manufacturing company is thinking about building a new factory. The factory, if built, will yield

the company $300 million in 7 years, and it would cost $220 million today to build. The company will decide to build the factory if the interest rate is

a. no less than 4.53 percent.

b. no greater than 4.53 percent.

c. no less than 5.81 percent.

d. no greater than 5.81 percent.

+2
Answers (1)
  1. 15 December, 17:03
    0
    B) no greater than 4.53 percent

    Explanation:

    We need to calculate the present value of $300 million using both discount rates:

    present value₁ = $300 / 1.0453⁷ = $220

    present value₂ = $300 / 1.0581⁷ = $202

    In order for a project to be accepted, its NPV ≥ 0, and only if we use the 4.53% discount rate will our project have a NPV of 0 ( = $220 - $220).

    So the company will decide to build the factory only if the interest rate (discount rate) is no greater than 4.53%.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A manufacturing company is thinking about building a new factory. The factory, if built, will yield the company $300 million in 7 years, ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.