Ask Question
6 April, 17:33

The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog.

A. True

B. False

+5
Answers (1)
  1. 6 April, 18:01
    0
    B-False

    Explanation:

    After the retrospective discussion all the improvement items discussed are placed in the Product Backlog. To ensure continuous improvement, the next sprint backlog (& not the current one) should include at least one high priority process improvement which was identified in the previous Sprint Retrospective meeting.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.