Ask Question
22 April, 17:53

In agile projects, overall planning is at a high level, and only the near-term work is planned in detail. The project work is conducted in iterations (sprints) that are normally: a. no more than one calendar year b. a variable length depending on project scope c. a fixed length of two or four weeks d. assigned to one person on the team

0
Answers (1)
  1. 22 April, 19:12
    0
    The answer is letter C.

    Explanation:

    A fixed length of two or four weeks.
Know the Answer?