Ship Co. produces storage crates that require 34.0 meters of material at $0.20 per meter and 0.30 direct labor hours at $19.00 per hour. Overhead is applied at the rate of $16 per direct labor hour. What is the total standard cost for one unit of product that would appear on a standard cost card?

+1
Answers (1)
  1. 19 August, 05:09
    0
    Total standard cost = $103.7

    Explanation:

    Standard cost is the sum of the standard material cost, standard labour cost and standard overhead

    Overhead = OAR * direct labour hour

    = $16 * (0.30*$19.00) = 91.2

    Standard cost = (34.0*$0.20) + (0.30*$19.00) + 91.2 = $103.7

    Standard cost = $103.7
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Ship Co. produces storage crates that require 34.0 meters of material at $0.20 per meter and 0.30 direct labor hours at $19.00 per hour. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers