Ask Question
7 January, 09:02

San Juan, Inc. is considering two alternatives: A and B. The costs associated with the alternatives are listed below: Alternative A Alternative B Material costs $ 38,000 $ 66,000 Processing costs 43,000 66,000 Building costs 13,700 36,000 Equipment rental 20,700 20,700 If only the differential costs of the two decisions are considered, the total differential costs of Alternative B is

+2
Answers (1)
  1. 7 January, 09:30
    0
    Total differential cost = - $73300

    Explanation:

    Equipment rental is equal in both alternatives, so it is not relevant for making a decision.

    Costs Alternative A:

    Material costs $ 38,000

    Processing costs 43,000

    Building costs 13,700

    Total = $94700

    Costs Alternative B:

    Material costs $ 66,000

    Processing costs $66,00

    Building costs $36,000

    Total = $168,000

    Total differential cost = 168000-94700=$73300

    Alternative B costs $73300 more than Alternative A. Based only on this information, alternative A is better than alternative B.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “San Juan, Inc. is considering two alternatives: A and B. The costs associated with the alternatives are listed below: Alternative A ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.