Mountain Dental Services is a specialized dental practice whose only service is filling cavities. Mountain has recorded the following for the past nine months: Month Number of Cavities Filled Total Cost January 300 $5,000 February 650 6,050 March 325 5,200 April 475 5,750 May 550 6,050 June 575 6,200 July 600 6,250 August 350 5,100 September 700 6,600 Required: 1. Use the high-low method to estimate total fixed cost and variable cost per cavity filled. 2. Using these estimates, calculate Mountain's total cost for filling 450 cavities.

+3
Answers (1)
  1. 13 September, 18:44
    0
    Instructions are listed below

    Explanation:

    Giving the following information:

    Month, cavities, total cost:

    January 300 $5,000

    February 650 $6,050

    March 325 $5,200

    April 475 $5,750

    May 550 $6,050

    June 575 $6,200

    July 600 $6,250

    August 350 $5,100

    September 700 $6,600

    A)

    Variable cost per unit = (Highest activity cost - Lowest activity cost) / highest activity units - Lowest activity units)

    Variable cost per unit = (6600 - 5000) / (700 - 300) = $4

    Fixed costs = Highest activity cost - (Variable cost per unit * HAU)

    Fixed costs = 6600 - (4*700) = $3,800

    Fixed costs = LAC - (Variable cost per unit * LAU)

    Fixed costs = 5000 - (4*300) = $3,800

    B) Q = 450

    Total cost = 3800 + 450*4 = $5,600
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Mountain Dental Services is a specialized dental practice whose only service is filling cavities. Mountain has recorded the following for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.