Ask Question
4 December, 14:24

Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?

A. Because each individual order is a "temporary endeavor," each order is a project.

B. This is program management since there are multiple projects involved.

C. This is a recurring process.

D. Orders incurring revenue over $100,000 would be considered projects and would involve project management.

+1
Answers (1)
  1. 4 December, 14:35
    0
    B. This is program management since there are multiple projects involved.

    Explanation:

    A program manager manages multiple projects, and sometimes multiple programs while a project manager manages the teams responsible for fulfilling the project and achieving its deliverables
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers