Ask Question
26 October, 19:33

Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?

A. 3.

B. 5.

C. 6.

D. 8.

E. None of the above.

+1
Answers (1)
  1. 26 October, 19:43
    0
    Answer: 3

    Explanation:

    the theoretical minimum number of workstations is the sum of all tasks time divided by circle time.

    I. e sum of task time / circle time

    (4 + 6 + 7 + 2 + 6 + 5) / 10 = 3
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers