The critical path on a project can change as the project progresses. select one:

a. true

b. false

+2
Answers (1)
  1. 29 November, 06:52
    0
    The answer is True.

    In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

    Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.