Our company pays an average wage of $12 per hour to employees for printing and copying jobs, and allocates $18 of overhead for each employee hour worked. Materials are assigned to each job according to actual cost. If Job M-47 used $260 of materials and took 15 hours of labor to complete, what is the total cost that should be assigned to the job

+1
Answers (1)
  1. 9 January, 06:15
    0
    Job M-47 cost assinged $710

    Explanation:

    the cost is the sum of the three main component

    materials

    direct labor

    manufacturing overhead (MO)

    we will calculate each of this for the Job M-47 add them together to get total cost

    Job M-47

    material 260

    15 labor hours

    Direct Labor 15 labour hours x 12 labor rate = 180

    MO 15 labour hours x 18 overhead rate = 270

    Total Cost materials + labor + manufacturing overhead = 710
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Our company pays an average wage of $12 per hour to employees for printing and copying jobs, and allocates $18 of overhead for each ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.