Cavern Company's output for the current period results in a $5,250 unfavorable direct material price variance. The actual price per pound is $56.50 and the standard price per pound is $55.00. How many pounds of material are used in the current period?

+2
Answers (1)
  1. 28 July, 11:48
    0
    3,500 pounds

    Explanation:

    By applying the below formula we get:

    AQ (AP-SP)

    USD 5,250 (unfavorable price variance)

    USD 5,250 / (AP - SP) = AQ

    So,

    USD 5,250 / (USD 56.50 - USD 55.00)

    = 3,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Cavern Company's output for the current period results in a $5,250 unfavorable direct material price variance. The actual price per pound ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.