Miami solar manufactures solar panels for industrial use. the company budgets production of 5,000 units (solar panels) in july and 5,300 units in august. each unit requires 3 pounds of direct materials, which cost $6 per pound. the company's policy is to maintain direct materials inventory equal to 30% of the next month's direct materials requirement. as of june 30, the company has 4,500 pounds of direct materials in inventory, which complies with the policy. prepare a direct materials budget for july.

+3
Answers (1)
  1. 9 July, 05:16
    0
    The correct answer is $91,620.

    Explanation:

    According to the scenario, the given data are as follows:

    Budget production units = 5,000 units

    Pounds per unit = 3

    Cost per pound = $6

    Beginning inventory = 4,500 pounds

    So, first we calculate the material needed for production by using following formula:

    Material needed for production = Units * Pounds per unit

    = 5,000 * 3

    = 15,000

    Now we calculate the total material requirement by using following formula:

    Total material requirement = Material needed for production + 30% of next month requirement

    = 15,000 + ((5300 * 3) * 30%)

    = 15,000 + 4,770

    = 19,770

    So, material to be purchased can be calculated as:

    Material to be purchased = Total material requirement - Beginning inventory

    = 19,770 - 4500

    = 15,270

    So, Direct material cost can be calculated by using following formula:

    Total cost for direct material = Material to be purchased * Cost per pound

    = 15,270 * $6

    = $91,620
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Miami solar manufactures solar panels for industrial use. the company budgets production of 5,000 units (solar panels) in july and 5,300 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.