Shumpert, Inc., entered into a contract that was to take two years to complete, with an estimated cost of $900,000. The contract price was $1,300,000. Costs of the contract for 2018, the first year, totaled $675,000.

a. What was the gross profit reported by the percentage of completion method for 2016?

b. After the contract was completed at the end of 2017 at a total cost of $950,000, what was the gross profit reported by the percentage of completion method for 2017?

+3
Answers (1)
  1. 17 July, 04:02
    0
    Answer for Part A and Part B is as follows:

    Particulars 2016 year 2017 year

    Contract Price $13,00,000 $13,00,000

    Cost that has been incurred $675000 $950000

    Estimated cost to complete $225000 $0

    TOTAL COST $900000 $950000

    Expected Gross profit $400000 $350000

    Percentage that is completed 75 percent 100percent

    Gross profit to be recognised $300000 $50000

    Note: Calculations have been made according to the data and figures given in the question.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Shumpert, Inc., entered into a contract that was to take two years to complete, with an estimated cost of $900,000. The contract price was ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.