27. ___ is a method for developing the shortest schedule when the number or amount of available resources is fixed. a. Resource evaluation scheduling b. Resource monitoring c. Resource limited scheduling d. Resource leveling

+4
Answers (1)
  1. 9 August, 10:55
    0
    c. resource-limited scheduling

    Explanation:

    Resource - limited scheduling -

    As the name suggests,

    It refers to the method of scheduling the shortest schedule where the available resources are fixed, is referred to as the resource - limited scheduling.

    It is a specific method to implement the resource leveling strategy in any assignment or project.

    Hence, from the given information of the question,

    The correct answer is c. resource-limited scheduling.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “27. ___ is a method for developing the shortest schedule when the number or amount of available resources is fixed. a. Resource evaluation ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.