Ask Question
11 September, 08:04

Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:

Inspection time 0.6 days

Wait time (from order to start of production) 15.8 days

Process time 2.8 days

Move time 1.3 days

Queue time 3.9 days

Required:

1.

Compute the throughput time. (Round your answer to 1 decimal place.)

2.

Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to the nearest whole percentage (i. e., 0.12 should be entered as 12).)

+5
Answers (1)
  1. 11 September, 08:17
    0
    1. Throughput time is 8.6days

    2. Manufacturing cycle efficiency (MCE) for the quarter is 32.

    Explanation:

    1. Throughput time is made up of inspection time, queuing time, process time and moving time. The sum of these gives 8,6days

    2. Manufacturing cycle efficiency (MCE) is the value added time expressed as a percentage of throughput time. Normally, the value added time is the process time. Thus, MCE=Value added time/Throughput time
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers