The 50th repetition of a job is timed at 100 minutes. if the learning curve for this job is 90 percent, what is the estimated time for the 200th repetition of this job?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The 50th repetition of a job is timed at 100 minutes. if the learning curve for this job is 90 percent, what is the estimated time for the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.