Ask Question
21 September, 03:09

Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. What is the least amount of time that the project can be completed and how many resources are required to complete the work?

a. 16 days, 7 workers

b. 7 days, 5 workers

c. 5 days, 7 workers

d. 8 days, 3 workers

+5
Answers (1)
  1. 21 September, 03:31
    0
    Answer: c. 5 days, 7 workers

    Explanation: With the project requirements provided, and with the least of number of resources working on the task not less than the number of those assigned to the task.

    The least amount of time for the project to complete would be approximately 5 days, and the resources needed to complete the task would be approximately 7 workers.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers