Ask Question
28 August, 01:05

Daget Corporation uses direct labor-hours in its predetermined overhead rate. At the beginning of the year, the total estimated manufacturing overhead was $364,620. At the end of the year, actual direct labor-hours for the year were 24,000 hours, manufacturing overhead for the year was overapplied by $8,540, and the actual manufacturing overhead was $360,580.

The predetermined overhead rate for the year must have been closest to $___ per direct labor-hour.

+3
Answers (1)
  1. 28 August, 01:34
    0
    The predetermined overhead rate for the year must have been closest to $15.38 per direct labor-hour.

    Explanation:

    Estimated Overhead = $364,620

    Actual Labor hours = 24,000 hours

    Over applied overhead = Applied overhead - Actual overhead

    $8,540 = Applied overhead - $360,580

    Applied overhead = $8540 + $360,580 = $369,120

    Applied overhead = Actual Labor hours x Predetermined overhead rate

    $369,120 = 24,000 x Predetermined overhead rate

    Predetermined overhead rate = $369,120 / 24,000 = $15.38 per labor hour