Christopher's cranks uses a machine that can produce 100 cranks per hour. the firm operates 12 hours per day, five days per week. due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 95% of the available time. based on experience with other products, the firm expects to achieve an efficiency level for the cranks of 85%. what is the expected weekly output of cranks for this company?

a. 5100

b. 5700

c. 4845

d. 969

e. 6783

+5
Answers (1)
  1. 28 August, 10:25
    0
    Given:

    No. of cranks per hour = 85 cranks, since the firm expects to achieve an efficiency level for the cranks

    No. of hours in the week = [ (12 x 5) x 95%] = 57 hours, since only 95% of the machine running time because of preventive maintenance

    Therefore, the expected weekly output of cranks for

    this company is = 85 cranks x 57 hours

    = 4845 cranks (c)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Christopher's cranks uses a machine that can produce 100 cranks per hour. the firm operates 12 hours per day, five days per week. due to ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.