Ask Question
3 February, 12:48

Three processes have the following costs: Process A has a fixed cost of $2,000 and variable cost of $3.00/unit. Process B's fixed cost is $4,000 and variable cost is $2.60/unit. Process C's fixed cost is $8,000 and variable cost is $2.40/unit. If the projected total demand is for 6,000 units, which process should be used?

+2
Answers (1)
  1. 3 February, 12:58
    0
    Process B should be used.

    Explanation:

    Total Cost = Fixed Cost + Variable Cost

    Total Cost = Fixed Cost + (Average Variable Cost) x (Quantity)

    Process A : TC = 2000 + (3) x (6000) = 2000 + 18000

    = $ 20000

    Process B : TC = 4000 + (2.60) x (6000) = 4000 + 15600

    = $ 19600

    Process C : TC = 8000 + (2.40) x (6000) = 8000 + 14400

    = $ 22400

    Since Total Cost for producing 6000 units quantity demanded is least by Process B, Process B should be used.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Three processes have the following costs: Process A has a fixed cost of $2,000 and variable cost of $3.00/unit. Process B's fixed cost is ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers