For Gundy Company, units to be produced are 5,280 in quarter 1 and 6,400 in quarter 2. It takes 2.0 hours to make a finished unit, and the expected hourly wage rate is $15 per hour. Prepare a direct labor budget by quarters for the 6 months ending June 30, 2020.

+3
Answers (1)
  1. 16 December, 20:43
    0
    Total cost = $350,400

    Explanation:

    Giving the following information:

    For Gundy Company, units to be produced are 5,280 in quarter 1 and 6,400 in quarter 2. It takes 2.0 hours to make a finished unit, and the expected hourly wage rate is $15 per hour.

    Quarter 1:

    Direct labor cost = 5,280*2 = 10,560 hours

    Quarter 2:

    Direct labor cost = 6,400*2 = 12,800 hours

    Total cost = (10,560 + 12,800) * 15 = $350,400
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “For Gundy Company, units to be produced are 5,280 in quarter 1 and 6,400 in quarter 2. It takes 2.0 hours to make a finished unit, and the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.