Ask Question
12 November, 00:36

Max and Lew have entered into a contract for Lew to paint Max's house. The contract specifically states that the job was to be completed by August 25. Lew completes the job on August 26. Max has suffered no loss due to the delay. The job was otherwise done exactly to all contract requirements and specifications. If Max sues Lew for breach of contract due to the missed completion date and if the courts were to award damages, what type of damages would most likely be awarded? Multiple Choice punitive damages consequential damages restitution nominal damages

+1
Answers (1)
  1. 12 November, 00:54
    0
    The correct answer is letter "D": nominal damages.

    Explanation:

    Nominal damages are granted as monetary rewards when a legal fault takes place but there has not been substantial damage because of it. It is said that the fact of granting the fault represents more of a moral act. Usually, if awarded, the plaintiff may receive $1 or $2.

    In the case, as Max suffered no loss because of Lew's delay while painting his house, if he decides to sue him he will be awarded nominal damage for the contract breach.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Max and Lew have entered into a contract for Lew to paint Max's house. The contract specifically states that the job was to be completed by ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers