Zitrik Corporation manufactured 90,000 buckets during February. The variable overhead cost-allocation base is $5.05 per machine-hour. The following variable overhead data pertain to February:

Actual Budgeted

Production 90,000 units 90,000 units

Machine-hours 9,800 hours 9,000 hours

Variable Overhead Cost per Machine-hour $5.15 $5.05

What is the variable overhead spending variance?

+4
Answers (1)
  1. 8 September, 11:42
    0
    1. What is the variable overhead spending variance? (HINT: The answer $980 unfavorable, but I need work to support this)

    2. What is the variable overhead efficiency variance? (HINT: The answer is $4,040 unfavorable, but I need work to support this)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Zitrik Corporation manufactured 90,000 buckets during February. The variable overhead cost-allocation base is $5.05 per machine-hour. The ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.