The Botosan Factory has determined that its budgeted factory overhead budget for the year is $13,500,000 and budgeted direct labor hours are 10,000,000. If the actual direct labor hours for the period are 350,000, how much overhead would be allocated to the period?

a.$472,500

b.$675,000

c.$236,250

d.$470,630

+3
Answers (1)
  1. 16 September, 18:30
    0
    a.$472,500

    Actual factory overhead applied = $ 1.35 * 350,000 = $ 472,500

    Explanation:

    Choice a is the correct answer. Actual factory overhead applied = $ 1.35 * 350,000 = $ 472,500

    Working

    Budgeted factory overhead budget for the year is $13,500,000

    Budgeted direct labor hours are 10,000,000.

    Budgeted factory overhead budget per hour for the year is = $13,500,000/10,000,000 = $ 1.35 per hour

    Actual direct labor hours for the period are 350,000

    Actual factory overhead applied = $ 1.35 * 350,000 = $ 472,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The Botosan Factory has determined that its budgeted factory overhead budget for the year is $13,500,000 and budgeted direct labor hours ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.