The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value. True False

+3
Answers (1)
  1. 30 October, 20:57
    0
    False

    Explanation:

    The burndown chart is a visual analysis tool used in projects execution to express the work completed daily against the outstanding purposely to ensure that project are completed and delivered with the agreed timeline.

    It measures effort in relation to the level of work done and also keep the team on daily schedule.

    The chart represents the work done on the vertical (Y) axis and the time on the horizontal (X) axis.