You have determined that a 75 percent learning curve is appropriate for a task. if the initial timing of the person performing that job was 50 minutes, and if you need the job performed 500 times, how many minutes of work will be required

+1
Answers (1)
  1. 28 September, 17:30
    0
    The answer is 3,184 minutes.

    According to the data, with a 75% learning curve, where the first unit is 1, the cumulative time to produce 500 units is 63.68 minutes.

    Given that where the first unit took 50 minutes

    Thus, the total time will be;

    50 x 63.68

    =3,184 minutes
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “You have determined that a 75 percent learning curve is appropriate for a task. if the initial timing of the person performing that job was ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.