Leaky Pipe Inc. Daily demand = 600 Work 50 weeks a year. 300 days a year Order Cost $10 a year. Holding Cost per year $1 What's the Time Between Orders Group of answer choices Between 7.0 to 7.5 days Between 7.5 to 8.0 days Between 8.0 to 8.5 days Between 6.5 to 7.0 days None of the above
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Leaky Pipe Inc. Daily demand = 600 Work 50 weeks a year. 300 days a year Order Cost $10 a year. Holding Cost per year $1 What's the Time ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.