A bottling plant fills 1,200 bottles every two hours. The lead time is 60 minutes and a container accommodates 130 bottles. The safety stock is 20 percent of the expected demand. How many kanban cards are needed? (Round up your answer to the next whole number.)

+3
Answers (1)
  1. 27 July, 12:45
    0
    6

    Explanation:

    Given that

    Annual Demand = 10 bottles in 1 minute

    Leading time = 60 minute

    percentage of Safety stock = 0.2

    Container size = 130 bottles

    The computation of the number of kanban cards is given below:-

    = Annual demand * Leading time (1 + percentage of safety stock) : Container size

    = 10 * 60 (1 + 0.2) : 130

    = 600 (1.2) : 130

    = 5.538

    So, the round-up the next whole number is 6
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A bottling plant fills 1,200 bottles every two hours. The lead time is 60 minutes and a container accommodates 130 bottles. The safety ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.