Miel Company produces ready-to-cook oatmeal. Each carton of oatmeal requires 16 ounces of rolled oats per carton (the unit quantity standard) and 0.04 labor hour (the unit labor standard). During the year, 960,000 cartons of oatmeal were produced.

Required:

1. Calculate the total amount of oats allowed for the actual output.

ounces

2. Calculate the total amount of labor hours allowed for the actual output.

hours

+3
Answers (1)
  1. 29 April, 00:58
    0
    Part A

    1) Total amount of oats allowed = 960000*16 = 15360000 ounce

    2) Total amount of labor hours allowed

    = 960000*.04 = 38400 Hours

    Part B:

    1) Total amount of oats allowed = 750000*17 = 12750000 ounce

    2) Total amount of labor hours allowed

    = 750000*.04 = 30000 Hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Miel Company produces ready-to-cook oatmeal. Each carton of oatmeal requires 16 ounces of rolled oats per carton (the unit quantity ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.