The person most qualified to assess the overall risk in a work package activity in a project is the:

+5
Answers (1)
  1. 15 April, 11:54
    0
    The person most qualified to assess the overall risk in a work package activity in a project is the team member and / or line manager.

    The team member cannot be the only one who will assess such risks - he will need to be accompanied by the line manager, or the manager can do it on his own. PR and sponsors do not deal with such actions - PR deals with public relations, and sponsors with giving money.