Painting: 2 hours (including dry time of 1.5 hours)
The company uses departmental overhead rates. Overhead is allocated at the rate of $6/direct labor hour in Sanding, and $15/machine hour in Machining. Painting overhead is allocated on the basis of total time in the department and is allocated at a rate of $3/hour.
How much overhead is allocated to the job?
a. $78
b. $67.50
c. $45
d. $72
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Machining: 4 hours (all automated) Sanding: 1 hour (all direct labor) Painting: 2 hours (including dry time of 1.5 hours) The company uses ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.