Ask Question
27 December, 23:59

A company is creating a product where the production line is made up of single machine stations where the throughput rates are not quite equal. The bottleneck rate of the line is 787 tons per 8 hour day, and the raw process time is 2 hours. The line has averaged 659 tons per day, and the flow time has averaged 3.5 hours. What is the estimated average WIP for the product line

+3
Answers (1)
  1. 28 December, 00:17
    0
    WIP = 288.3125 tons

    Explanation:

    Work in process is also called goods in process or in process inventory. It is all unfinished goods that are being processed by a company that will eventually be completed and sold.

    Production per hour = average product per day : production hours per day

    Production per hour = 659 : 8 = 82.375 tons

    Work in process = Production per hour * Flow time

    WIP = 82.375 * 3.5 = 288.3125 tons
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A company is creating a product where the production line is made up of single machine stations where the throughput rates are not quite ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.