Crane WaterWorks manufactures snorkel gear. During the past month, Washington purchased 4,130 pounds of plastic to use in its dive masks, at a cost of $5,972. The standard price for the plastic is $1.433 per pound. The company actually used 4,060 pounds of the plastic to produce 18,500 dive masks.

a. Calculate crane waterworks direct materials price variance for the month.

+1
Answers (1)
  1. 24 August, 00:27
    0
    Direct material price variance = $53.69 unfavorable

    Explanation:

    Giving the following information:

    Actual purchase = 4,130 pounds of plastic

    Actual cost = $5,972 (total)

    The standard price for the plastic is $1.433 per pound.

    The company used 4,060 pounds of the plastic to produce 18,500 dive masks.

    To calculate the direct material price variance, we need to use the following formula:

    Direct material price variance = (standard price - actual price) * actual quantity

    Actual price = 5,972/4,130 = $1.446

    Direct material price variance = (1.433 - 1.446) * 4,130 = $53.69 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Crane WaterWorks manufactures snorkel gear. During the past month, Washington purchased 4,130 pounds of plastic to use in its dive masks, ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.