car wash services 200 customers in an hour on a lovely Saturday afternoon. The car wash employs 5 washers at $6 per hour and uses $50 of water and $5 of electricity per hour. An appropriate measure of productivity is A. 80%. B. 0.425 $/car. C. 8 cars/$. D. 2.35 cars/$.

+3
Answers (1)
  1. 31 May, 23:07
    0
    Productivity = 2.35 cars / $

    Explanation:

    Given:

    Total number of car per hour = 200

    Total number of washers = 5

    Wages per hour each washer = $6

    Per hour water expenses = $50

    Per hour electricity expenses = $5

    Computation of total expenses per hour:

    Total expenses per hour = (Total number of washers x Wages per hour) + Per hour water expenses + Per hour electricity expenses

    Total expenses per hour = (5 x $6) + $50 + $5

    Total expenses per hour = $30 + $50 + $5

    Total expenses per hour = $85

    Computation of productivity:

    Productivity = Total number of car per hour / Total expenses per hour

    Productivity = 200 / $85

    Productivity = 2.35 cars / $
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “car wash services 200 customers in an hour on a lovely Saturday afternoon. The car wash employs 5 washers at $6 per hour and uses $50 of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.