Job 303 includes direct materials costs of $ 540 and direct labor costs of $ 400. If the predetermined overhead allocation rate is 50 % of direct labor cost, what is the total cost assigned to Job 303?

+4
Answers (1)
  1. 8 April, 21:18
    0
    Total cost will be $1140

    Explanation:

    We have given direct material cost = $540

    Direct labor cost = $400

    And overhead allocation is 50 % of direct labor cost

    So overhead allocation = 50 % of $400 = $200

    We have to find the total cost assigned to the job

    So total cost = direct material cost + direct labor cost + overhead allocation = $540 + $400 + $200 = $1140

    So total cost will be $1140
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Job 303 includes direct materials costs of $ 540 and direct labor costs of $ 400. If the predetermined overhead allocation rate is 50 % of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.