Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process. bullet

Step 1: 25 minutes per unit bullet

Step 2: 15 minutes per unit bullet

Step 3: 30 minutes per unit bullet

Step 4: 20 minutes per unit Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 105 units?

+2
Answers (1)
  1. 24 January, 08:41
    0
    the hours after roundinf off = 54 hours

    Explanation:

    Solution:

    The rate of system is defined by machine with largest time per unit i. e. bottleneck resource.

    In this case, biottleneck is Step : 3 with time 30 min per unit.

    So system requires 30 * 105 min = 30 * 105 / 60 hours = 52.5 hours at bottleneck.

    time for first unit at Step 1 and 2 and for last unit at step 4 is - 25 + 15 + 20 - 60min - 1 hr.

    So total time for system is 52.5 + 1 = 53.5 hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.