Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus Development Co. Relevant data are summarized below: Contract amount $ 2,550,000 Cost: 2017 1,100,000 2018 500,000 Gross profit: 2017 650,000 2018 300,000 Contract billings: 2017 1,275,000 2018 1,275,000 ADH recognizes revenue upon completion of the contract. What is the journal entry in 2018 to record revenue?

+4
Answers (1)
  1. 13 March, 20:40
    0
    The Journal entry is as follows:

    Construction in progress A/c Dr. $950,000

    Cost of construction A/c Dr. $1,600,000

    To revenue from long term contracts $2,550,000

    (To record the revenue in 2018)

    Workings:

    Cost of construction:

    = cost of 2017 + cost of 2018

    = $1,100,000 + $500,000

    = $1,600,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Arizona Desert Homes (ADH) constructed a new subdivision during 2017 and 2018 under contract with Cactus Development Co. Relevant data are ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers