The following information is available for Ivanhoe Company. April 1 April 30 Raw materials inventory $10,500$14,000 Work in process inventory 4,8403,700 Materials purchased in April $97,700 Direct labor in April 80,300 Manufacturing overhead in April 162,000 Prepare the cost of goods manufactured schedule for the month of April.

+2
Answers (1)
  1. 11 November, 02:19
    0
    Answer and Explanation:

    The preparation of the cost of goods manufactured schedule for the month of April is presented below

    Beginning work-in-process inventory $4,840

    Manufacturing costs:

    Direct materials:

    Beginning inventory $10,500

    Purchases $97,700

    Materials available $108,200

    Less: Ending inventory - $14,000

    Direct materials used $94,200

    Direct labor $80,300

    Manufacturing overhead $162,000

    Total manufacturing costs: $336,500

    Total costs of work-in-process $341,340

    ($4,840 + $341,340)

    Less: Ending work-in-process - $3,700

    Cost of goods manufactured $337,640

    Basically we simply the cost of goods manufactured formula
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The following information is available for Ivanhoe Company. April 1 April 30 Raw materials inventory $10,500$14,000 Work in process ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.