Ask Question
29 April, 02:20

On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $39,200 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $19,600 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $19,600 to Green. Revis estimates an 80% chance that cost savings will reach the target and calculates the contract price based on the expected value of future payments to be received.

+4
Answers (1)
  1. 29 April, 02:40
    0
    The contract price based on the expected value of future payments to be received is $246,960

    Explanation:

    The computation of the expected value is shown below:

    For meeting the target, it will equal to

    = (Received amount * number of months + additional amount) * probability rate

    = ($39,200 * 6 months + $19,600) * 80%

    = $203,840

    For not meeting the target, it will equal to

    = (Received amount * number of months - additional amount) * remaining probability rate

    = ($39,200 * 6 months - $19,600) * 20%

    = $43,120

    So, the total expected value would be

    = $203,840 + $43,120

    = $246,960
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.