Is typically not referred to as a buffer type in critical chain project management?

+2
Answers (1)
  1. 31 October, 02:30
    0
    The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

    Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.