Shelton Co. purchased a parcel of land six years ago for $876,500. At that time, the firm invested $148,000 in grading the site so that it would be usable. Since the firm wasn't ready to use the site itself at that time, it decided to lease the land for $55,500 a year. The company is now considering building a warehouse on the site as the rental lease is expiring. The current value of the land is $928,000.

Required:

1. What value should be included in the initial cost of the warehouse project for the use of this land?

a) $876,500b) $928,000c) $0d) $1,024,500e) $1,076,000

+1
Answers (1)
  1. 19 February, 18:39
    0
    Answer:Answer to Shelton Co. purchased a parcel of land six years ago for $876500. At that time, the ... At That Time, The Firm Invested $148,000 In Grading The Site So That It Would Be Usable. Since The Firm Wasn't Ready To Use The Site Itself At That Time, It Decided To Lease The Land For $55,500 A Year.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Shelton Co. purchased a parcel of land six years ago for $876,500. At that time, the firm invested $148,000 in grading the site so that it ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers