Ask Question
18 October, 09:08

You have just been assigned as project manager for a large telecommunications project. This one year project is about halfway done. The project team consists of five sellers and 20 of your company's employees. You want to understand who is responsible for doing what on the project. Where would you find such information?

A. Responsibility assignment matrix

B. Resource histogram

C. Bar chart

D. Project organization chart

+3
Answers (1)
  1. 18 October, 09:35
    0
    Answer: (A) Responsibility assignment matrix

    Explanation:

    Responsibility assignment matrix is plays an important role for completing the project as it describe about the business process and the participation for completing the various types of given task.

    The main objective of the responsibility assignment matrix is that it assign the role for each participant for completing the given project. It is also known as the responsibility accountability matrix or the RACI matrix.

    According to the given question, the project manager assign a project related to the telecommunication and by using the responsibility assignment matrix we can easily find out the role of the each participant in the given project.

    Therefore, Option (A) is correct.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “You have just been assigned as project manager for a large telecommunications project. This one year project is about halfway done. The ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers