Ceelo Company purchased (at a cost of $9,630) and used 1,800 pounds of materials during May. Ceelo's standard cost of materials per unit produced is based on 3 pounds per unit at a cost $5.50 per pound. Production in May was 510 units. (a) Compute the total, price, and quantity variances for materials. Total Materials Variance $ Materials Price Variance $ Materials Quantity Variance $

+2
Answers (1)
  1. 24 January, 21:01
    0
    Answer and Explanation:

    The computation is shown below:

    Material price variance

    = (Actual quantity * Actual price) - (Actual quantity * Standard price)

    = ($9,630) - (1,800 * $5.50)

    = $270 favorable

    Material quantity variance

    = (Actual quantity * Standard price) - (Standard quantity * Standard price)

    = (1,800 * $5.50) - [ (510 * 3) * $5.5]

    = $9,900 - $8,415

    = $1,485 unfavorable

    Total material variance

    = Material price variance + material quantity variance

    = $270 unfavorable + $1,485 unfavorable

    = $1,215 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Ceelo Company purchased (at a cost of $9,630) and used 1,800 pounds of materials during May. Ceelo's standard cost of materials per unit ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.