Ask Question
9 April, 01:45

The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,118. A total of 40 direct labor-hours and 257 machine-hours were worked on the job. The direct labor wage rate is $18 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $22 per machine-hour. The total cost for the job on its job cost sheet would be:

a. $5,867

b. $10,637

c. $8,492

d. $5,448

+2
Answers (1)
  1. 9 April, 01:49
    0
    Option (c) is correct.

    Explanation:

    Given that,

    Direct materials cost = $2,118

    Total direct labor-hours = 40

    Total machine hours = 257

    Direct labor wage rate = $18 per labor-hour

    Predetermined overhead rate = $22 per machine-hour

    Total cost for the job:

    = Direct materials cost + Direct labor cost + Overhead cost

    = $2,118 + (40 hours * $18 per hour) + (257 hours * $22 per machine hour)

    = $2,118 + $720 + $5,654

    = $8,492
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,118. A total of 40 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers