Elwood Company applies overhead based on machine hours. At the beginning of the year, Elwood estimates overhead to be $760,000, machine hours to be 200,000, and direct labor hours to be 40,000. During February, Elwood has 3,750 direct labor hours and 16,000 machine hours. If the actual overhead for February is $58,300, what is the overhead variance, and is it overapplied or underapplied?

+3
Answers (1)
  1. 13 August, 12:53
    0
    Overhead variance is $ 2,500 Overapplied

    Explanation:

    Computation of applied overhead rate based on machine hours

    Estimated Overhead $ 760,000

    Estimated machine hours 200,000 hours

    Overhead Rate per machine hour = $ 760,000. 200,000 hours = $ 3,80

    Actual Machine hours for February 16.000

    Applied overhead based on machine hours $ 3.80 * 16,000 = $ 60,800

    Actual overhead for February $ 58,300

    Overhead variance - Over applied $ 2,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Elwood Company applies overhead based on machine hours. At the beginning of the year, Elwood estimates overhead to be $760,000, machine ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.