Ask Question
29 December, 12:41

The total direct labor hours required in preparing a direct labor budget are calculated using the: a. sales budget. b. sales forecast. c. direct materials budget. d. production budget.

+1
Answers (1)
  1. 29 December, 12:52
    0
    Answer:is correct

    Option d

    Production budget

    Explanation:

    The total direct labour hours budget are prepared using the production budget. It shows the expected amount o time in hours that are required to achieved the production budget

    The direct labour hours budget =

    production budget (units) * standard direct labour hours per unit

    The standard direct labour hours is the expected amount amount of time a unit of the product is expected to be produced

    The production budget in turn is prepared using sales budget and finished goods inventory budget.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The total direct labor hours required in preparing a direct labor budget are calculated using the: a. sales budget. b. sales forecast. c. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers