Johnson's rule gives optimal answer for what type of scheduling problems?

+5
Answers (1)
  1. 2 October, 00:59
    0
    The answer is two-machine flow shop. The two-machine flow shop issue in which each activity is prepared through an in-house framework or outsourced to a subcontractor. A calendar is set up for the in-house employments, and execution is measured by the makespan.