In Year 1, a contractor agrees to build a building for $850,000 by the end of Year 2. The builder's cost is estimated to be $400,000. The actual costs for Year 1 are $240,000 and Year 2's actual costs are $180,000. Under the percentage of completion method Year 1's gross profit is

+5
Answers (1)
  1. 13 February, 17:01
    0
    Under the percentage of completion method Year 1's gross profit is $270000.

    Explanation:

    Percentage of completion = Cost incurred upto date / total cost

    = $240,000/$400,000

    = 60%

    Estimated gross profit = Contract price - Estimated cost

    = $850,000 - $400,000

    = $450000

    Year 1 gross profit = $450000*60% = $270000

    Therefore, Under the percentage of completion method Year 1's gross profit is $270000.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In Year 1, a contractor agrees to build a building for $850,000 by the end of Year 2. The builder's cost is estimated to be $400,000. The ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.